DAY 1
All Covid-19 checks, and inductions completed, now ready to begin. Cables landed and now to pull in over 2000 metres of HV cable.
All about being prepared for the task today!
DAY 2
Continued pulling in legs for the install of a HV ring to feed 4x 1750kVA transformers from customer substation.
Managed to pull in 3 legs of the HV ring today in tough conditions, but it’s what we do!
1000 metres of cable, all in a day’s work for the lads.
DAY 3
We all got a little dirty today!😮
Continued installing the HV ring ready for the transformers to land tomorrow. Then we can commence the HV terminations.
DAY 4
The transformers have arrived, we began landing them ready for HV terminations and made a start on installing earth nests.
DAY 5
Finished installing substation nests and made a start on HV terminations.
DAYS 6-7
🥶Tough conditions, but we still managed to terminate 10 HV ends.
DAYS 8-10
2 x HV joints and fitted switchgear, all phased out and pressure tested.